1. Section 90 and the Polavaram Project Authority
Section 90(1) declares the Polavaram Irrigation Project a National Project, while Section 90(3) mandates the Central Government to execute the project and obtain requisite environmental, forest, and R&R clearances. Under Section 90(4), the Polavaram Project Authority (PPA) was constituted in May 2014 under the Ministry of Jal Shakti, with the Government of Andhra Pradesh executing works on the Centre's behalf.
- Polavaram is a multi-purpose project on the Godavari river linking Godavari waters to the Krishna basin.
Timeline
May 2014
PPA constituted; Ordinance issued for transfer of 7 Khammam submergence mandals.
Jul 2014
AP Reorganisation (Amendment) Act, 2014 enacted by Parliament.
Sep 2016
Centre agrees to 100% funding of remaining irrigation component as on 1 April 2014 via NABARD LTIF.
2020–24
Flood damage to diaphragm wall prompts CWC/PPA review and renewed central support.
2. Transfer of Seven Mandals (2014 Amendment Act)
Because the reservoir's submergence zone extended into seven mandals of Khammam district in Telangana, the Centre promulgated an Ordinance in May 2014 and Parliament enacted the AP Reorganisation (Amendment) Act, 2014 in July 2014 transferring those seven mandals (excluding Bhadrachalam revenue village/temple town) to East and West Godavari districts of Andhra Pradesh.
- Enabled unified state administration over both dam construction and submergence R&R.
Polavaram Execution & Reimbursement Cycle
- 1. AP executes works under PPA oversight
- 2. Bills verified by PPA & CWC
- 3. Reimbursement routed via NABARD LTIF
- 4. R&R completion enables phased storage up to 45.72 m FRL
3. Funding Norms, R&R Safeguards and Technical Hurdles
In September 2016, the Centre committed to 100% funding of the remaining irrigation component as on 1 April 2014 via NABARD's Long-Term Irrigation Fund (excluding the power component). Revised Cost Estimates escalated largely due to higher R&R entitlements under the LARR Act, 2013 and Fifth Schedule tribal safeguards. Technically, the 2020 Godavari floods damaged the diaphragm wall, requiring CWC/PPA expert remediation, while Odisha and Chhattisgarh raised backwater submergence concerns.
- Design FRL: 45.72 m (150 ft); phased impoundment depends on R&R colony completion.
| Dimension | Key Fact |
|---|---|
| Statute | Section 90, AP Reorganisation Act, 2014 |
| Oversight Body | Polavaram Project Authority (PPA), Ministry of Jal Shakti |
| Territorial Amendment | 7 Khammam mandals transferred via 2014 Amendment Act |
| Funding Rule | 100% of remaining irrigation component as on 1 April 2014 (NABARD LTIF) |
| R&R & Inter-State | LARR Act 2013 + Fifth Schedule; Odisha & Chhattisgarh backwater studies |
Real-world case studies
2020 Diaphragm Wall Damage
High Godavari flood discharges damaged the diaphragm wall, highlighting the engineering complexity of executing a mega earth-cum-rockfill dam across a major peninsular river.
Previous year questions
No source-linked PYQ is available here yet. Use the practice questions below.
Practice questions
Practice MCQ 1 · Easy
Under which Section of the AP Reorganisation Act, 2014 is Polavaram declared a National Project?
- Section 84
- Section 85
- Section 89
- Section 90
Practice MCQ 2 · Easy
What is the cutoff date for 100% Central funding of Polavaram's remaining irrigation component?
- 1 April 2014
- 2 June 2014
- 1 April 2015
- 1 September 2016
Practice MCQ 3 · Easy
Which two neighbouring states raised backwater submergence concerns over Polavaram?
- Karnataka and Tamil Nadu
- Odisha and Chhattisgarh
- Maharashtra and Madhya Pradesh
- Kerala and Karnataka
Mains practice · Discuss the statutory basis, funding architecture, R&R safeguards and technical/inter-state challenges of the Polavaram National Project under Section 90 of the AP Reorganisation Act, 2014.
- Section 90 & PPA
- 2014 Amendment Act (7 mandals)
- 1 April 2014 100% irrigation funding & NABARD LTIF
- LARR Act 2013, Fifth Schedule, diaphragm wall & Odisha/Chhattisgarh backwater issues
Further reading
- The Andhra Pradesh Reorganisation Act, 2014 — Section 90.
- Polavaram Project Authority (PPA) official portal.
Preparing for APPSC Group 1 or Group 2? See the APPSC Groups coaching course at Pragnya IAS Academy for fees, batches and registration.
Long study hours taking a toll? Try the free breathing exercise and self check-in in Pragnya’s student wellness programme for UPSC aspirants.