
Construction workers and a crane in Andhra Pradesh
Credit: Narendra Modi · CC BY 3.0 · source
1. Meaning, assumptions and CSAT relevance
Time and work belongs to basic numeracy and can also appear within a data interpretation or reasoning problem. The wording may concern labourers building a wall, machines producing components, typists processing records or pipes filling a tank. Despite these different settings, the mathematical structure remains the same: a quantity of work is produced at a specified rate over a period of time.
The governing equation is Work = Rate × Time. If the whole job is represented by 1 and A finishes it in 12 days, A's rate is 1/12 job per day. If B finishes the same job in 18 days, B's rate is 1/18 job per day. Working together, they complete 5/36 of the job per day and therefore require 36/5, or 7.2 days.
Standard aptitude questions normally assume a constant work rate, identical work quality, uninterrupted availability and no loss of efficiency from working together. These are modelling assumptions, not universal facts about workplaces. If a question specifies fatigue, machine breakdowns, learning effects or interference between workers, those conditions replace the usual assumptions.
- Identify whether the question asks for elapsed time, actual working time, workforce size, efficiency or completed work.
- Use a consistent time unit throughout: days, hours or minutes.
- Do not add completion times to calculate joint completion time; add rates.
2. Unit-work method, LCM method and efficiency
The unit-work method takes total work as 1. The least common multiple, or LCM, method instead selects a convenient total that makes individual rates integers. For completion times of 12 and 18 days, choose 36 work units. A produces 3 units daily and B produces 2. Their combined rate is 5 units daily, so completion takes 36/5 days. The LCM is a computational convenience, not a separately given physical quantity.
For two workers completing the same task independently in x and y days, their joint time is xy/(x + y). This follows from adding 1/x and 1/y and taking the reciprocal. For three or more workers, adding rates is safer than memorising additional formulae. Also, if A and B together take t days while A alone takes a days, B's rate is 1/t − 1/a.
Efficiency means output per unit time. If A:B efficiency is 3:2, their times for the same job are in the ratio 2:3. If A is 25% more efficient than B, their rate ratio is 5:4 and their time ratio is 4:5. Thus, A takes 20% less time, not 25% less time. This distinction is a frequent source of errors.
- Use fractional rates when denominators are simple or total work is already normalised.
- Use LCM units when several workers have different integer completion times.
- Given rates for A+B, B+C and C+A, add them and divide by 2 to obtain the rate of A+B+C.
Six-step solution process
- 1. Identify the total task, initial conditions and required unknown.
- 2. Choose total work as 1 or a convenient LCM.
- 3. Convert completion times into rates with consistent units.
- 4. Split changing schedules into stages or complete cycles.
- 5. Calculate remaining work and the time or workforce needed.
- 6. Check signs, final partial periods and the plausibility of the answer.
3. Changing teams, alternate days and partial completion
When workers join or leave, split the job into stages. Calculate work completed in each stage, subtract it from total work, and divide the remainder by the next stage's rate. Suppose A takes 10 days and B takes 15 days. With total work set to 30 units, their rates are 3 and 2 units daily. If A works alone for 2 days, 24 units remain. Together they finish these in 24/5 days, making total elapsed time 6.8 days.
Alternate-day problems require attention to the starting worker and the order of work. Suppose A completes a job in 6 days and B in 12 days, working on alternate days with A starting. Choose 12 units: A does 2 daily and B does 1. Each two-day cycle completes 3 units. After three cycles, 9 units are complete; A adds 2 on day 7 and B finishes the last unit on day 8.
Do not mechanically divide total work by average daily output in an alternating schedule. Whole cycles may be grouped, but the last incomplete cycle must be checked day by day. For example, a worker beginning the final day may complete the remaining work before the next worker's turn. Fractional final days are normally allowed unless the question restricts work to full shifts or indivisible tasks.
- Record the work remaining after every team change.
- Distinguish completion during the nth day from completion after n full days.
- Check whether a percentage refers to total work or only to the work remaining.
| Situation | Relationship | Condition |
|---|---|---|
| Individual work | Rate = Total work / Time | Rate is constant over the stated interval |
| Two workers together | Time = xy/(x + y) | Each independently completes the same job in x and y time units |
| Efficiency comparison | Time ratio is the inverse of the rate ratio | Total work is identical |
| Workforce comparison | Work ∝ Workers × Days × Hours × Efficiency | Output is additive and work is comparable |
| Filling with leakage | Net rate = Inlet rate − Outlet rate | Both operate simultaneously at the stated constant rates |
4. Worker-days, working hours and wages
For equally efficient workers, output is proportional to the number of workers and their working time. If daily hours also vary, use Work = k × Workers × Days × Hours per day, where k is output per worker-hour. For different groups, an efficiency multiplier may be included. The general comparison is W1/W2 = (M1 × D1 × H1 × E1)/(M2 × D2 × H2 × E2), provided the work is comparable.
For example, 12 equally efficient workers working 6 hours daily for 10 days supply 720 worker-hours. To complete the same work in 5 days at 8 hours daily, the required workforce is 720/(5 × 8) = 18. If the second team must complete 50% more work under the same conditions, it needs 27 workers. A worker-day alone is insufficient when working hours change.
When payment is explicitly proportional to work contributed, divide wages according to rate multiplied by actual time worked. If A and B have efficiencies 3:2 and work for 4 and 6 days respectively, their contributions are 12:12, so payment is shared equally. However, an hourly wage contract may produce a different division. Never assume work-linked payment when the question specifies a different rule.
- For fixed work and unchanged hours and efficiency, workers × days is constant.
- For fixed workforce and efficiency, more work requires proportionately more time.
- Round workforce requirements upward when a whole number of workers is necessary to meet a deadline.
5. Pipes, cisterns and a reliable solving strategy
Pipes and cisterns are time-and-work problems in which tank capacity replaces total work. An inlet filling a tank in x hours has rate +1/x tank per hour; an outlet emptying a full tank in y hours has rate −1/y. A pipe filling in 6 hours and an outlet emptying in 9 hours yield a net filling rate of 1/18 tank per hour, so an initially empty tank fills in 18 hours.
Initial conditions matter. If that tank is already one-third full, only two-thirds remains, requiring 12 hours at the same net rate. If the outlet rate equals the inlet rate, the water level does not rise under the constant-rate model. If outflow exceeds inflow, the tank cannot fill from empty. These conclusions assume the stated rates apply while the pipes operate; real discharge rates can vary with water pressure.
A dependable examination approach is to label total work, individual rates and elapsed time before calculating. Choose convenient work units, organise any schedule into stages, and use the options for a final plausibility check. Two positive-rate workers together must finish sooner than either alone. Adding a leak must increase filling time. Increasing workforce while holding work, hours and efficiency fixed must reduce completion time. Such checks detect many arithmetic and interpretation errors.
- Avoid premature decimal conversion; fractions often preserve accuracy.
- Apply signed rates only while the relevant inlet, outlet or worker is active.
- Treat indivisible outputs and sequential operations separately when simultaneous work is not possible.
Real-world case studies
MGNREGA: person-days and physical output
MGNREGA reporting uses person-days to measure employment generated. This is a real administrative application of counting labour input, but person-days are not automatically a measure of completed physical work. Soil conditions, task type, tools and worksite organisation affect output. The CSAT lesson is to distinguish labour input from work completed and to use proportionality only when comparable productivity is assumed.
Urban water storage and pumping
Municipal service reservoirs receive water through pumping or gravity systems while supplying distribution networks. Their storage balance follows the same principle as a cistern problem: change in stored volume equals inflow minus outflow over time. Real systems have changing demand and pumping schedules, so calculations may require several time intervals rather than one constant net rate.
Previous year questions
No source-linked PYQ is available here yet. Use the practice questions below.
Practice questions
Practice MCQ 1 · Easy
A can complete a survey in 18 days and B can complete the same survey in 36 days. If they work together at their respective constant rates, how many days will they take to complete it?
- A. 9 days
- B. 12 days
- C. 15 days
- D. 27 days
Practice MCQ 2 · Easy
A is 25% more efficient than B. If B alone can complete a task in 20 days, how many days will A alone take to complete the same task?
- A. 15 days
- B. 18 days
- C. 16 days
- D. 25 days
Practice MCQ 3 · Easy
Fifteen equally efficient workers can repair a road in 12 days. How many days will 18 such workers take to repair the same road, if daily working hours remain unchanged?
- A. 10 days
- B. 8 days
- C. 14 days
- D. 15 days
Practice MCQ 4 · Easy
A and B together can digitise a set of records in 8 days. A alone can digitise the same set in 24 days. How many days will B alone take?
- A. 16 days
- B. 10 days
- C. 18 days
- D. 12 days
Practice MCQ 5 · Easy
The efficiencies of A and B are in the ratio 2:3. A works for 4 days and B works for 6 days on a project. If ₹5,200 is distributed between them in proportion to the work each completes, what is A's share?
- A. ₹2,080
- B. ₹1,600
- C. ₹2,600
- D. ₹3,600
Practice MCQ 6 · Moderate
A can complete a job in 12 days and B can complete it in 18 days. They work together for 3 days, after which A leaves. B completes the remaining job alone. What is the total time taken from the start?
- A. 10½ days
- B. 12 days
- C. 13½ days
- D. 15 days
Practice MCQ 7 · Moderate
A alone can finish a task in 9 days and B alone in 12 days. They work on alternate days, with A working on the first day. They stop as soon as the task is complete, allowing a fractional final working day. What is the total elapsed time?
- A. 10 days
- B. 10½ days
- C. 11 days
- D. 10¼ days
Practice MCQ 8 · Moderate
Sixteen workers, working 6 hours daily, can complete a construction assignment in 15 days. A second assignment involves 50% more work. How many equally efficient workers are needed to complete the second assignment in 12 days, working 9 hours daily?
- A. 20 workers
- B. 18 workers
- C. 24 workers
- D. 30 workers
Practice MCQ 9 · Moderate
Two inlet pipes can separately fill an empty tank in 12 hours and 18 hours. An outlet can empty the full tank in 36 hours. Both inlets are opened together when the tank is empty. After 3 hours, the outlet is also opened, and all three remain open until the tank is full. Assuming constant rates, how long does filling take from the start?
- A. 7¼ hours
- B. 8¼ hours
- C. 9 hours
- D. 10½ hours
Practice MCQ 10 · Moderate
A and B together can complete a job in 12 days, B and C together in 15 days, and C and A together in 20 days. Their individual rates remain constant. How many days will C alone take to complete the job?
- A. 30 days
- B. 40 days
- C. 60 days
- D. 120 days
Practice MCQ 11 · Difficult
A project was planned to be completed by 24 workers in 20 days, working 6 hours daily. After 5 days of work, its total scope was increased by 25% of the original scope, and 6 workers left. Work then stopped completely for 2 days. On resumption, the remaining workers and some newly recruited workers work 8 hours daily. Each new worker is 75% as efficient per hour as an original worker. What is the minimum number of new workers required to finish by the original deadline?
- A. 10 workers
- B. 12 workers
- C. 14 workers
- D. 13 workers
Practice MCQ 12 · Difficult
At their normal rates, A and B together can finish a job in 10 days, B and C together in 15 days, and C and A together in 12 days. They follow a repeating three-day schedule: A and B work on the first day, B and C on the second, and C and A on the third. After the first 6 days, C's efficiency becomes half its normal value for the rest of the job; A's and B's efficiencies remain unchanged. Allowing a fractional final day, when will the job be completed?
- A. After 12½ days
- B. After 12 days
- C. After 13 days
- D. After 13½ days
Practice MCQ 13 · Difficult
Inlet A alone can fill a tank in 8 hours and inlet B alone in 12 hours when there is no leakage. With a leak active, both inlets together fill the empty tank in 6 hours. Starting with an empty tank and the leak active throughout, both inlets are opened for 2 hours. A is then closed for 3 hours while B remains open. Thereafter, A is opened for one hour and closed for one hour alternately, starting with an open hour, while B remains continuously open. Assuming all rates are constant, what is the total time from the start until the tank is full?
- A. 9¼ hours
- B. 9¾ hours
- C. 10¼ hours
- D. 10¾ hours
Practice MCQ 14 · Difficult
A is 50% more efficient than B, while C is 50% as efficient as B. A and B work together for the first 4 days of a job. B and C work together for the next 3 days. A and C then work together until the job is complete. A total payment of ₹16,400 is divided strictly in proportion to each person's contribution. If A's payment and B's payment are in the ratio 3:2, what is C's payment?
- A. ₹2,000
- B. ₹2,800
- C. ₹3,200
- D. ₹2,400
Practice MCQ 15 · Difficult
At their normal constant rates, A and B together can complete a job in 8 days. A alone takes 12 days less than B alone. They initially work together at normal rates for 3 days. B then leaves, and A works alone for 4 days at 75% of A's normal efficiency. Thereafter, they work on alternate days, with B working first. B works at the normal rate, but A continues at the reduced rate. Allowing a fractional final day, what is the total elapsed time from the start?
- A. 13⅔ days
- B. 14 days
- C. 14⅓ days
- D. 14⅔ days
Further reading
- UPSC official website: Civil Services Examination notification, Preliminary Examination scheme and syllabus.
- UPSC official website: Previous Question Papers, Civil Services Preliminary Examination, General Studies Paper II.
- NCERT Mathematics, Class VIII: Direct and Inverse Proportions.
- NCERT Mathematics, Class VII: Comparing Quantities.
- Ministry of Rural Development: MGNREGA official portal and employment-generation reports.
Preparing for UPSC Civil Services? Get classroom teaching, answer-writing evaluation and mentorship at Pragnya IAS Academy, Ashok Nagar — see why aspirants choose us for IAS coaching in Hyderabad.
