Quick answer
Andhra Pradesh's electricity system combines thermal, hydro and renewable generation. Official reporting put installed capacity near 30,500 MW at the end of 2025, with renewables and hydro together close to half the total — but capacity is a stock measure, not generation or supply adequacy.
Installed capacity is a stock measure; actual generation, availability and supply adequacy vary over time.
Always quote the reporting date with a capacity figure.
Map · Andhra Pradesh
Power system anchors
- 1. Kurnool region — solar — Regional locator only
- 2. Anantapur region — solar and wind — Regional locator only
- 3. Srisailam region — hydel — Reservoir-region locator
Illustrative city coordinates indicate regional functions, not exact plant sites.
- Illustrative city and region points only; they do not represent boundaries or exact mine, well or facility sites.
Installed capacity by source, 31 December 2025
30,502 MW
All sources combined
15,666 MW
Thermal (coal, gas, diesel)
3,290 MW
Hydro
11,546 MW
Renewables
Where the renewable capacity sits, 30 September 2025
| Source | Installed (MW) | Note |
|---|---|---|
| Solar | 5,772 | Ground-mounted parks dominate |
| Wind | 4,398 | Concentrated in the Rayalaseema plateau |
| Large hydro | 3,050 | Reservoir-linked stations |
| Bio-power | 594 | Bagasse and biomass |
| Small hydro | 163 | Minor stations |
| Total renewable | 13,977 | Includes large hydro |
Generation lenses
Thermal
- Includes state, central and private stations.
- Coastal siting supports fuel logistics but brings environmental constraints.
Hydel
- Srisailam Right Bank (770 MW) is the largest state-station group.
- Lower Sileru 460 MW, Upper Sileru 240 MW, Nagarjunasagar Right Canal 90 MW and its tail pond 50 MW follow.
- Hydropower output is affected by inflows and competing water-use priorities.
Renewables
- Kurnool Ultra Mega Solar Park contributes 1,000 MW at Panyam.
- NP Kunta in Anantapur reports 978.5 MW of a planned 1,500 MW.
- Solar and wind add variable generation that needs storage and transmission.
Solar parks named in official and developer reporting
| Park | District | Capacity (MW) | Status note |
|---|---|---|---|
| Kurnool Ultra Mega Solar Park | Kurnool | 1,000 | Operational; developed by APSPCL |
| NP Kunta | Anantapur | 978.5 of 1,500 | Partly commissioned |
| Ananthapuramu-II | Tadipatri, Anantapur | 500 | Operational |
| Galiveedu | Kadapa | 250 of 1,000 | Partly commissioned |
Do not conflate
Statements examiners like to twist — learn the correct version.
Installed MW equals annual energy supplied.
Capacity factor, outages and hydrology determine output.
Every announced storage scheme is sanctioned.
Distinguish proposal, appraisal, approval, construction and operation.
Prelims focus
- Differentiate capacity and generation.
- Name the largest state hydel station group.
Mains angle
- Assess renewables' contribution to Andhra Pradesh's power mix and the balancing needs it creates.
Flip & recall
Answer in your head first, then tap the card to check.
Practice MCQs
Original Prelims-style questions with explanations.
0 / 3 correct · 3 left
Q1.Installed capacity is measured as
Q2.Hydel output depends strongly on
Q3.Pumped storage primarily provides