Quick answer
In September 2016, the Centre agreed to fund 100% of the remaining irrigation component cost of Polavaram as on 1 April 2014, routed through NABARD's Long-Term Irrigation Fund.
While National Projects normally receive 90% central assistance for irrigation components, the Centre agreed in September 2016 to fund 100% of the remaining irrigation component of Polavaram as on 1 April 2014.
Central Funding Scope vs State Concerns
Central Position
1 April 2014 cutoff
- 100% funding of remaining irrigation component as of 1 April 2014
- Routed via NABARD Long-Term Irrigation Fund (LTIF)
State Concerns
Revised Cost Estimates
- Higher R&R outlay under LARR Act, 2013
- Timely reimbursement of state-incurred expenditure
Funding Rules and Policy Debates
| Parameter | Position |
|---|---|
| Funding Share | 100% Central funding of remaining irrigation component as on 1 April 2014. |
| Funding Channel | NABARD Long-Term Irrigation Fund (LTIF) on reimbursement basis via PPA. |
| Exclusions | Power generation component and drinking water components are excluded from 100% irrigation funding. |
| Cost Escalation Debate | Higher R&R costs under the LARR Act, 2013 and Revised Cost Estimates (RCE) led to prolonged AP–Centre reconciliation. |
Flip & recall
Answer in your head first, then tap the card to check.
Practice MCQs
Original Prelims-style questions with explanations.
0 / 3 correct · 3 left
Q1.The Centre's 100% funding commitment for Polavaram covers the remaining irrigation component as on:
Q2.Central funding for Polavaram was routed through which NABARD facility?
Q3.Which factor significantly increased Polavaram's Revised Cost Estimate (RCE)?