Economic Survey 2025-26 reports 509.74 GW installed power capacity in November 2025; rural daily supply rose from 12.5 hours in FY14 to 22.6 in FY25.
Installed power capacity is the rated instantaneous output of generating plants, not the electricity actually delivered to consumers. India’s larger generation fleet and distribution investment have improved availability, but reliable supply also requires transmission, transformers and functioning local networks.
Concept diagram
Power Sector: Capacity Addition and Supply
Power supply is a connected chain from generating plants through transmission networks to demand centres.
- Installed MW measures potential power, not electricity generated.
- Reliable supply also depends on networks, fuel and system operations.
Power-system basics: separate three measurements
MW and kWh
- MW or GW measures power: 1 GW = 1,000 MW. A kWh measures energy delivered over time; capacity is not generation.
- Actual energy depends on utilisation, fuel, weather, maintenance and grid constraints.
MVA and circuit-kilometres
- MVA measures apparent-power handling capacity of transformers; it is not directly interchangeable with generating MW.
- Circuit-kilometres measure transmission circuits, not necessarily the geographic length of a corridor.
Data chart
Generation additions accelerated in the first eight months
Source: Economic Survey 2025-26, Chart IX.15 (CEA, Executive Summary Report, November 2025) · Values transcribed from chart labels; comparable April–November periods.
Show the data (MW)
| Period / item | Generating capacity added |
|---|---|
| Apr–Nov FY25 | 15,008 |
| Apr–Nov FY26 | 40,939 |
Grid additions did not move uniformly
| Chart IX.15 indicator | Apr–Nov FY25 | Apr–Nov FY26 |
|---|---|---|
| Transformation capacity addition (MVA) | 38,805 | 60,260 |
| Transmission line addition (circuit-km) | 5,117 | 3,641 |
| Installed generation stock, November 2025 | — | 509.74 GW; 11.6% year-on-year growth |
Data chart
Daily supply hours improved most in rural India
- FY14
- FY25
- The rural–urban availability gap narrowed sharply.
- Averages do not guarantee continuous supply at every individual connection.
Source: Economic Survey 2025-26, Chart IX.16 (Ministry of Power) · Values read from the Survey chart; approximate.
Show the data (Hours per day)
| Period / item | FY14 | FY25 |
|---|---|---|
| Rural | 12.5 | 22.6 |
| Urban | 22.1 | 23.4 |
Access investments: distinguish villages, households and projects
| Programme or outcome | Survey evidence |
|---|---|
| DDUGJY, IPDS and SAUBHAGYA | About ₹1.85 lakh crore invested in distribution infrastructure |
| DDUGJY | 18,374 villages electrified |
| SAUBHAGYA period | 2.86 crore households gained electricity access |
| RDSS, launched 2021 | ₹3.03 lakh crore outlay; ₹2.8 lakh crore projects approved |
| Energy demand–supply gap | 4.2% in FY14 to nil by November 2025 |
Move from connection to dependable service
Create access
Use household connections and distribution assets to reach previously unserved users.
Match network capacity
Coordinate new generation with transformers and transmission; additions in one segment cannot replace another.
Measure service quality
Monitor interruptions, voltage and local reliability alongside national supply hours and aggregate adequacy.
Electricity adequacy is not identical to reliability
Statements examiners like to twist — learn the correct version.
509.74 GW is electricity generated during November.
It is installed generating capacity as of November 2025, a stock measured in GW.
A nil national energy gap means every household has 24-hour power.
Aggregate demand–supply balance can coexist with local outages and less than 24-hour average supply.
All grid additions accelerated in FY26.
Chart IX.15 shows lower transmission circuit-km addition in April–November FY26 than in the comparable FY25 period.
Prelims focus
- Learn GW versus kWh, MVA and circuit-km.
- Rural supply: 12.5 to 22.6 hours; urban: 22.1 to 23.4 hours, FY14–FY25.
Mains angle
- Discuss why electricity access, adequacy and quality require different indicators.
- Explain how uneven grid investment can constrain the economic benefits of faster capacity addition.
Flip & recall
Answer in your head first, then tap the card to check.
Practice MCQs
Original Prelims-style questions with explanations.
0 / 3 correct · 3 left
Q1.Which unit measures electrical energy rather than power?
Q2.Which addition fell in Apr–Nov FY26 compared with Apr–Nov FY25?
Q3.A nil aggregate energy demand–supply gap necessarily establishes: